Moving the Steps

Yet more progress was made outside of the church this week. The following has been achieved during the four working days of the week:


✔ The week started with the repositioning of the stone steps to make space for the new disabled ramp.

The two lower steps were fixed in place and the restraining concrete block walls were
constructed before laying the upper treads.


By the end of the week all five treads had been replaced. The original steps had slightly sunk over time such that they were tilting backwards. This had the unfortunate result of holding any rainfall at the back of the treads. Having now repositioned the steps correctly has consequently increased the overall height slightly, causing the top step to be higher
than the path.

The path was to have been raised slightly anyway to form a slight ramp up to the porch entrance, but it has meant that the bottom hinges for the gates will need to be removed and positioned higher.


✔ Meanwhile inside, Derek continued fixing two layers of plasterboard to the rear walls of the toilet cubicle, which will eventually be skimmed with plaster.


✔ Simon Beisly, the electrician, began the first fix this week, which included locating
wiring for the sockets and switches in both the toilet and kitchen areas.


It has been suggested that a time capsule be buried behind the retaining walls around the lift area. Recommendations have been received as to what the capsule should contain.

Access to the church will continue to be closed while internal work continues.

John Pinch
23 April 2022

Open 2 All Logo

A Path on an Arc

This week continues to see real progress outside of the church. The following has been achieved during the four working days of last week:

✔ Concrete was mixed on site and poured into the three spaces between the shuttering that was installed at the end of last week. The three sections are to accommodate the incline, which will form the edging to the disabled ramp.


✔ A more accurate arc was plotted on the new concrete foundations to form the building line for a double wall comprising concrete blocks at the back and solid dressed stone for the facing.


✔ A row of concrete blocks were laid on the curve on top of the concrete that will serve to hold back the earth between the new wall and the existing church boundary wall. More concrete will be poured into the gap after the concrete blocks have cured
to underpin the existing church wall, because the foundations are insignificant.

✔ Dressed Cotswold stone blocks were laid in front of and tied into the concrete blocks to form the final facing of the wall. A small return (corner) was created to finish off the wall where it meets the tarmac path up to Church Cottage.

✔ More clay at the abutment with the road was removed with the digger to provide a wider parking space for a hearse or disabled vehicle. This area will be dug down 20cm lower than the road, and filled with Type One (gravel) to form a base for
tarmac, which will extend the width of the road.


The area inside the back of the church was cleared to provide access for the Easter Sunday service via the west entrance door.

John Pinch
18 April 2022

Open 2 All Logo

The Digger Comes

Week 5 – report of work for disabled access, toilet and kitchen 4th April – 8th April

This week has seen real progress outside of the church. The following has been achieved within the last week:

✔ A digger and dumper truck arrived on site and work started by removing the old tree stump.

W5-P1

✔ Soil and clay were dug out of the left bank, adjacent to the north entrance steps and deposited temporarily in the church field.

✔ The stone steps were loosened and gently transported to rest in the church field until the site is ready to reposition them.

✔ Using a laser, the levels for the ramp were set out prior to construction work. The radius for the ramp was marked out taking into consideration the low walls on each side of the path. At this point, whilst driving in a peg to support the shuttering, Will
discovered yet another drain! This one ran in the direction of Church Farmhouse and was damp, suggesting it is still operational. The covering stones were carefully replaced after inspection and recorded by camera.

✔ A line was set up to mark the gentle slope of the disabled ramp, and surprised us that the gradient was finally recorded at only 1 in 25, where 1 in 12 is the maximum slope. Two horizontal landings were included because there has to be one at the
start of the ramp, and the regulations dictate that a resting place must be included every five metres, hence we have included another halfway up the slope.

✔ Shuttering was set up to form a framework into which concrete will later be poured for the foundations of the low walls. More concrete will be poured behind the low walls to underpin the existing stone wall above. The existing foundations for the church wall are minimal!

✔ The hole under the font was filled-in and re-tiled using four redundant original tiles from the back of the toilet and secured with lime mortar and grouting. The residual cement mortar that was used to fix the font in place will be removed with
brick acid.

✔ Time was spent discussing and designing the plumbing system for the toilet and kitchen and the effect this will have on the studwork and plasterboard behind the toilet. A small cupboard will be included to allow access to the water stop tap. Similarly, the hole in the toilet floor was filled in and re-tiled using lime mortar.

✔ Derek carefully removed the hinges on the internal arched door with the help of an impact driver. It was decided to fit a new lock and door handles once the door is rehung to open in the opposite direction into the church.

✔ Derek, with John in his workshop have made good progress during the week, cutting the oak tongue and groove and gluing together the first of four new gates. Work also continued cutting the mortise and tenon joints on the second gate.

✔ Jon and John collected three sheets of oak faced board at the end of the week, that will be used to clad the outside of the toilet cubicle.

The main entrance to the north of the church remains closed until further notice, due to ground works for the new re-designed disabled ramp.

Access to the church and grounds will be possible via the west entrance adjacent to the Old Parsonage, as well as through the two small footpath gates.

John Pinch
9 April 2022

Open 2 All Logo

Progress inside and out

Week 4 – report of work for disabled access, toilet and kitchen

This week has seen progress both inside and outside of the church. The following has been achieved within the last week:

✔ A connection to the existing water pipe was made in the trench outside, by first isolating the supply at the stop tap in the road.

✔ A new stop tap was positioned where the blue water pipe emerged through the hole in the wall, and above ground level in the toilet area.

✔ An inspection chamber was concreted and installed in the trench above the gas pipe. The ground was filled in around it, leaving just the lid of the inspection chamber visible. The trench arch will be eventually excavated from this position for a
length of 15 metres downhill, passing under the gravel path towards the yew tree. A mechanical digger will be used.

✔ The associated pipes and bends from the back of the toilet and basins was arranged in the corner of the toilet area. Type 1 (gravel) was tipped in the hole with some of the original spoil to a level 100mm below finished inside floor level.
Limecrete will be laid to bring the final level up to 25mm below floor level to enable the floor tiles to be relocated.

✔ Following a second visit from the archaeologist on Monday, more bone specimens were inspected as well as the ancient trench that was discovered in the lift well at the end of last week. Seemingly, it is of no great significance, and so the
ground in the lift area continued to be excavated to a depth of 30cm below the existing threshold tiled floor level and tube covered with a geotextile fabric. More Type 1 was then barrowed and tipped in bringing the level up to 21cm below final
floor level. The gravel was compacted with a vibrating plate, before covering with 12 cm of limecrete.

✔ The walls and ceiling of the toilet cubicle were clad with two layers of plasterboard, but the cavity left for the electrician to do a first fit of the wires and trunking that will happen on 13 April.

✔ The font is to be repositioned adjacent to the column by the new kitchen. The holy water from the font usually exits down into the ground after a christening. However, to save digging a new hole in the church floor, it has been decided to
close off the plug hole in the font and insert a bowl for holding the christening water. Following the service, the water will be scattered in the church grounds.

✔ Derek, with John in his workshop have made good progress during the week, where they are making a new set of oak gates for the re-designed north entrance.

The main entrance to the north of the church will be closed from Tuesday, 5th April until further notice, due to ground works starting for the new re-designed disabled ramp.

Access to the church and grounds will be possible via the west entrance adjacent to the Old Parsonage, as well as the two small footpath gates.

John Pinch
2 April 2022

Open2All Logo

Excavations and Finds

Week 3 – report of work for disabled access, toilet and kitchen

Although work has been confined mainly to the inside of the church, we have made significant progress during this third week. The following has been achieved:

✔ With the help of Derek, the pair of us cut some of the mortise and tenon joints that will form the pair of new oak gates for the north entrance.

✔ The font was moved to a temporary position by jacking it up and inserting steel rollers beneath. A 12” square hole was revealed beneath and we have shown the archaeologist the discovery. Some of the stones that were used to fill the void were interesting. One piece, in particular looked like it was carved to form a boss from a vaulted ceiling. Another couple of pieces of stone were dressed and showed signs of soot. My theory is that the roof of the parvis room might have once been stone vaulted before replacing it with a wooden structure and covered in lead. There is still a short chimney stack, indicating that a fireplace was part of the east wall. I believe the small stones we found under the font were redundant parts from this refurbishment. Russell and Roger worked on cleaning up the tiles after moving the font.

✔ Richard Cherrington, the archaeologist also inspected the shallow hole in the corner of the toilet area. Having removed some of the floor tiles and excavated to a depth of approximately .5 metre prior to his arrival, the dig revealed a large flat stone. Whilst Richard monitored the continuation of the dig, we were disappointed to find nothing of any significance beneath.
Digging finally ceased at a depth of 1.2M.

✔ Will, and his two employees Jon and Doug, used machinery to remove the ceramic tiles and limecrete that I laid on the rubble floor over twenty years ago when myself and a team of villagers removed the seven short pews by the bell tower. Fortunately, limecrete is not as difficult to remove as the much harder concrete might have been. An area approximately 3M x 1.4M was dug by hand and the spoil tipped on the grass on the right of the north front approach steps. One or two small pieces of bone were discovered as well as remnants of cut and faced stone that had been previously used for one reason or another.

Digging to a depth of 30cm below existing porch floor level, Will discovered a small flat cut piece of stone. Upon lifting the stone, he discovered a stone trench, or culvert of approximately 25cm square cross-section. Knowing that the porch is the oldest remaining part of the church, and that the floor level of the main section of the church was raised, this culvert would have been just below ground level. However, it is more interesting that it continues on a curve, passing beneath the steps up to the belfry. Hence, it must be rather old. Richard, the archaeologist is anxious to inspect this discovery when he visits again next Monday.

✔ The investigatory trench to locate the water pipe on the south side of the church also served to accommodate the large diamond drilling machine that was needed to drill two holes through the south wall. Confirming my suspicions, the trench finally exposed a water pipe at a depth of over 90cm, having first revealed the gas pipe and a very large clay drain of approximately
20cm diameter. I believe this pipe carries the water from the two downpipes from the south wall gutter to an eventual soak away, somewhere else in the graveyard.

On Friday, the drilling company drilled the two holes through the wall from outside. The first hole is at an external depth of 30cm below ground level to pierce the inside face of the 75cm thick wall in the toilet area, some 1.3M below inside floor level to facilitate the soil pipe for the toilet and basin wastes. This hole will also accommodate the new water pipe, having first connected it to the existing blue water pipe outside, under the gas pipe. A second hole, 12.5cm diameter, was drilled approximately 2M high in the same area for the extractor fan.
Altogether, a very satisfying exercise…
John Pinch

Open 2 All Logo

Progressing Well

New approach to the west gate

The Open 2 All Project is progressing well. A lovely new approach to the west gate of the church with oak steps and Cotswold gravel top has been made. All carefully done by Will Heming.

Work inside

It’s only Open 2 All day two and the work on the new loo has also started by John, Derek and John.

Wood Pile

Open 2 All Project Update 07/03/2022

We have started!

The Open 2 All project is officially underway. The oak for cladding the WC cubicle and for making two sets of new gates for the church was collected from the sawmills last Monday and is now stacked in the back of the church.

The area at the back of the church has been cordoned off in readiness for working on the WC cubicle.

All the other construction materials will be delivered on Tuesday 8th March where Derek Crocker, John Brown and myself will set-to building the stud partition walls.

Meanwhile, Will Heming and John Wallis will be re-landscaping the west approach to the church next to Heidi’s house.

Photos include the oak at the sawmills and finally on the floor in the church.

John Pinch

Wood Pile